Abstract: Selection and equipment was done on tunnelling machinery, mechanized operating line was equipped based on current technical force of mine, drivage technology was optimized, parallel operation mode was adopted in construction organization, thus high-speed drivage of mining laneway under geological condition of compound soft-rock was realized, difficult mine connection problem was solved effectively.
Key words: Compound soft-rock, Mining laneway, High-speed drivage, Mechanization
YE Ping, CAO Jing, QIN Guang-Peng. Mining Laneway High-speed Drivage Technology under CompoundSoft-rock Roof and Floor Finite Deformation[J]. Modern Mining, 2012, 28(05): 9-11.