某矿井通风系统优化方案研究

刘东锐1,2 李永辉1,2 李松徽1,2   

  1. 1. 长沙矿山研究院有限责任公司;2. 国家金属采矿工程技术研究中心
  • 出版日期:2025-09-25 发布日期:2025-11-04

Research on Optimization Scheme of Mine Ventilation System

  1. 1. Changsha Institute of Mining Research Co.,Ltd.; 2. National Engineering Research Center for Metal Mining Technology
  • Online:2025-09-25 Published:2025-11-04

摘要: 为保障葚沟矿区矿工安全,提高矿工的作业效率,针对矿区井下通风系统存在的系 统不完善、通风不足等问题,通过现场调查、数据分析及理论计算等方法提出了-240~280 m 中段隔 离通风、分区通风、单元通风 3 种可选方案,并结合矿区实际情况,分别对 3 种方案释放的风量、风 阻及风机选型等参数进行对比,得出以下结论:方案一东翼风量 42 m³/s,风机静压效率 72.5%,西翼 风量 47 m³/s,风机静压效率 77.5%;方案二东翼风量 45 m³/s,风机静压效率 76.0%,西翼风量 47 m³/s, 风机静压效率 77.5%;方案三东、西翼主扇风量 41.71 m³/s,对容易及困难时期各参数进行分开计算。 通过对这3个通风方案在技术、经济方面的比较,方案二的工程及设备费用总和较方案一多64.54万 元,较方案三多 135.37 万元,但其进回风线路更可靠、通风阻力最小、运行费用最少,综合各方面考 虑,选择方案二作为该矿区井下通风系统的优化方案。方案实施后,各通风技术指标均达到了相关 规定的合格标准,空气质量得到了较大改善,通风效率显著提高,能耗大幅降低,保证了矿井的安全 生产。

关键词: 金属矿山, 地下开采, 矿井通风, 系统优化

Abstract: To ensure the safety of miners in the Shenggou mining area and improve their working effi⁃ ciency,aiming at the problems such as incomplete system and insufficient ventilation existing in the under⁃ ground ventilation system of the mining area,three optional schemes,namely,isolation ventilation in the - 240~280 m middle section,zone-based ventilation and unit ventilation,were proposed through on-site in⁃ vestigation,data analysis and theoretical calculation methods. Combined with the actual situation of the min⁃ ing area,The parameters such as the air volume released,air resistance and fan selection of the three schemes were compared,and the following conclusions were drawn. Scheme One is that The air volume of the east wing is 42 m³/s,and the static pressure efficiency of the fan is 72.5%,the air volume of the west wing is 47 m³/s,and the static pressure efficiency of the fan is 77.5%. Scheme Two is that the air volume of the east wing is 45 m³/s,and the static pressure efficiency of the fan is 76.0%. The air volume of the west wing is 47 m³/s,and the static pressure efficiency of the fan is 77.5%. Scheme Three is that the air volume of the main fans in the east and west wings is 41.71 m³/s,and each parameter is calculated separately during the easy and difficult periods. Through the comparison of these three ventilation schemes in terms of technol⁃ ogy and economy,the total engineering and equipment cost of Scheme Two is 645 400 yuan more than that of Scheme One and 1 353 700 yuan more than that of Scheme Three. However,its intake and return air lines are more reliable,the ventilation resistance is the smallest,and the operating cost is the lowest. Considering all aspects comprehensively,Scheme Two is selected as the optimization scheme for the underground venti⁃ lation system in this mining area. After the implementation of the plan,all ventilation technical indicators have reached the qualified standards stipulated by relevant regulations. The air quality has been greatly im⁃ proved,the ventilation efficiency has been significantly enhanced,and the energy consumption has been greatly reduced,ensuring the safe production of the mine.

Key words: metal mine, underground mining, mine ventilation, system optimization