刚果(金)某氧化铜钴矿石取代硫化铜钴矿石的选矿工艺改造

庄国锋1 王金良2 陈炳宇1 魏红波2 刘邦1   

  1. 1. 科米卡矿业简易股份有限公司;2. 北方矿业有限责任公司
  • 出版日期:2022-10-25 发布日期:2023-05-23

The Beneficiation Processing Transformation for Copper-cobalt Oxide Ore Replacing Copper-cobalt Sulphide Ore in Democratic Republic of the Congo

ZHUANG Guofeng1 WANG Jinliang2 CHEN Bingyu1 WEI Hongbo2 LIU Bang1   

  1. 1. Komika Mining Simple Co.,Ltd.; 2. North Mining Limited Liability Company
  • Online:2022-10-25 Published:2023-05-23

摘要: 刚果(金)某硫化铜钴矿石选矿厂改为处理氧化铜钴矿石,选矿工艺需进行较大的调 整。为了推广本次改造的成功经验,介绍了具体改造内容和生产指标情况。具体改造内容:①碎 磨车间改造主要是将排矿口尺寸增大15 mm,将半自磨机的钢球填充率由10%降至7.5%,将球磨 机的钢球添加制度由添加ϕ60 mm单一钢球调整为ϕ60 mm和ϕ80 mm钢球各半添加,并降低球磨 机的钢球补加量。②浮选车间改造主要是由上下2 个区各自独立的1 粗2 扫3 精、中矿顺序返回流 程,改为两阶段六次开路粗选流程,即加药集中搅拌后连续3 次粗选流程、尾矿加药集中搅拌后再 连续3 次粗选流程;同时,加药点由每个作业加药改为每台浮选机加药,并增加一个搅拌桶,及对 原矿浆管道走向按流程进行调整。③脱水车间改造主要是调整浓密机转速、絮凝剂及其用量。改 造后氧化精矿铜、钴品位分别为10.74% 和1.07%,回收率分别为83.40% 和66.65%,达到了预期的 生产指标。

关键词: 氧化铜钴矿石, 选矿, 流程改造

Abstract: A copper-cobalt sulphide ore Dressing plant in Democratic Republic of the Congo altered to treat copper-cobalt sulphide ore,so the beneficiation process need to be adjusted widely. The specific retrofit content and production indexes situation were introduced so as to extent the successful transforma⁃ tion experience. The retrofit content was introduced as followed: ① The reform of grinding workshop is mainly to increase the size of 15 mm,reduce the filling rate of the steel ball of the semi-self-mill from 10% to 7.5%,adjust the steel ball addition of the ball mill from a single ϕ60 mm ball to ϕ60 mm and ϕ80 mm ball half and half,and reduce the amount of steel ball addition of the ball mill. ② The transformation of flotation workshop is mainly to change the independent process of one roughing,two scavenging,three cleaning and middling return in order in the upper and lower working areas into a two-stage process of six open circuit roughing,namely,three consecutive roughing processes after dosing centralized stirring,and three consecutive roughing processes after tailings dosing centralized stirring. At the same time,dosing was changed from each operation to each flotation machine,and a stirring drum was added to adjust the direc⁃ tion of slurry pipeline according to the flow. ③ The transformation of dehydration workshop is mainly to ad⁃ just the speed of thickener,flocculant and its dosage. The grade of copper and cobalt in oxidized concen⁃ trate after transformation is 10.74% and 1.07%,and the recovery is 83.40% and 66.65%,respectively, reaching the expected production indexes.

Key words: copper-cobalt oxide ore, beneficiation, process transformation