Modern Mining ›› 2013, Vol. 29 ›› Issue (08): 4-7.
Previous Articles Next Articles
Cheng Gaofu
Online:
Published:
Abstract: According to the actual conditions of the Gushan iron mine hang for ore, the Ⅱ stage mining scheme is designed. The mining sequence, method, ventilation, drainage , filling,compressed air, moving boundary are designed and calculated. The scheme can meet the production requirements,the hang for mineral resources can be fully recycled and the iron ore output is increased, to ensure the mineral resources of the Gushan iron mine.
Key words: Hang for ore mine, Upward slice stoping and backfilling mining method, Rock moving boundary
CHENG Gao-Fu. Mining Scheme Design of Gushan Iron Mine Hang for Ore Ⅱ Stage[J]. Modern Mining, 2013, 29(08): 4-7.