现代矿业 ›› 2026, Vol. 42 ›› Issue (03): 144-148.

• 岩土工程 • 上一篇    下一篇

采空区影响下露天采石场边坡稳定性评估及治理分析

孟 华1,2 陈 智3 王 勇4 欧阳志平5   

  1. 1. 长沙矿山研究院有限责任公司;2. 金属矿山安全技术国家重点实验室; 3. 新疆有色金属工业(集团)有限责任公司;4. 西部黄金克拉玛依哈图金矿有限责任公司; 5. 中建三局第三建设工程有限责任公司
  • 出版日期:2026-03-25 发布日期:2026-04-10

Stability Evaluation and Treatment Analysis of Open-pit Quarry Slope under the Influence of Goaf

  1. 1. Changsha Mining Research Institute Co.,Ltd.;2.State Key Laboratory of Metal Mine Safety Technolo‐ gy;3.Xinjiang Nonferrous Metals Industry (Group) Co.,Ltd.;4.Western Gold Karamay Hatu Gold Mining Co.,Ltd.;5.The Third Construction Co.,Ltd. of China Construction Third Engineering Bureau
  • Online:2026-03-25 Published:2026-04-10

摘要: 针对某露天采石场北侧边坡因历史采空区引发失稳坍塌的问题,采用数值模拟与极 限平衡法相结合的方法开展稳定性研究。首先利用 Midas 软件对北侧现状边坡进行模拟,发现其 在自重+地下水工况下的安全系数仅为 1.082,低于规范要求,且等效塑性应变最大值集中于采空 区周围,存在局部失稳风险。基于此,提出了排水疏干、削坡减载及采空区充填的综合治理方案。 治理后,利用基于极限平衡原理的简化 Bishop 法,对北侧边坡及基建完成后的东侧、南侧边坡,在 自重+地下水、叠加爆破振动、叠加地震力 3种工况下进行稳定性评估。结果表明:治理后北侧边坡 安全系数提升至 1.532(自重+地下水),东侧与南侧边坡在各工况下的安全系数范围分别为 1.230~ 1.641 和 1.323~2.038,均满足Ⅱ级边坡安全标准。三侧边坡在爆破工况下的安全系数均接近规范下 限,表明爆破扰动是影响边坡稳定性的最敏感因素。研究成果为矿山可持续安全生产提供了依 据,建议后续开采中采用预裂爆破、逐孔微差起爆及严格控制爆破安全距离等措施,以减小动态扰 动。

关键词: 露天矿, 边坡稳定性, 采空区治理, 安全系数, 爆破扰动

Abstract: Aiming at the problem of instability and collapse caused by historical goaf in the north slope of an open-pit quarry,the stability study is carried out by combining numerical simulation with limit equilibrium method. Firstly,Midas software is used to simulate the current slope on the north side. It is found that the safety factor under the condition of self-weight + groundwater is only 1.082,which is lower than the specification requirements,and the maximum equivalent plastic strain is concentrated around the goaf,which has the risk of local instability. Based on this,a comprehensive treatment scheme of drainage and drainage,slope cutting and load reduction and goaf filling is proposed. After the treatment,the simpli‐ fied Bishop method based on the limit equilibrium principle is used to evaluate the stability of the north slope and the east and south slopes after the completion of the infrastructure under three working condi‐ tions of self-weight + groundwater,superimposed blasting vibration and superimposed seismic force. The results show that the safety factor of the north slope is increased to 1.532 ( self-weight + groundwater ) after treatment. The safety factor ranges of the east and south slopes under various working conditions are 1.230~1.641 and 1.323~2.038,respectively,which all meet the safety standard of Grade II slope. The safety fac‐ tors of the three-sided slope under blasting conditions are close to the lower limit of the specification,indi‐ cating that blasting disturbance is the most sensitive factor affecting slope stability. The research results provide a basis for the sustainable and safe production of mines. It is suggested that pre-splitting blasting, hole-by-hole millisecond blasting and strict control of blasting safety distance should be adopted in subse‐ quent mining to reduce dynamic disturbance.

Key words: open-pit mine, slope stability, goaf management, safety factor, blasting disturbance