欢迎访问《现代矿业》杂志官方网站,今天是 分享到:
×

扫码分享

现代矿业 ›› 2026, Vol. 42 ›› Issue (07): 265-268.

• 实用技术 • 上一篇    

大直径深孔一步采矿房充填接顶方案优化研究与应用

王庆刚1,2 顾章恒1,2 张素娜1,2 王培培1,2 于兴社1,2 杨志强1,2   

  1. 1. 河钢集团沙河中关铁矿有限公司;2. 河北省复杂铁矿低碳智能高效开采技术创新中心
  • 出版日期:2026-07-25 发布日期:2026-08-17

Optimization Research and Application of Filling and Roof Contact Scheme for First-step Mining Chamber with Large-diameter Deep-hole

WANG Qinggang1,2 GU Zhangheng1,2 ZHANG Suna1,2 WANG Peipei1,2 YU Xingshe1,2 YANG Zhiqiang1,2   

  1. 1. Shahe Zhongguan Iron Mine Co.,Ltd.,Hebei Iron and Steel Group;2. Hebei Complex Iron Ore Low Carbon Intelligent and Efficient Mining Technology Innovation Center
  • Online:2026-07-25 Published:2026-08-17

摘要: 提高一步采矿房充填接顶效果,对于保障二步采矿房安全开采具有重要意义。针对 中关铁矿高阶段大直径深孔采场空区尺寸大、充填接顶效果差等难题,构建了采场充填料浆流动 模型,结合生产实践,分析充填料浆在空区内的沉降机理可知,当单点放料且充填料浆流动距离较 长时,在空区内,往往堆积成以放料口为中心的中间高、四周低的充填坡面,在此基础上,提出分段 充填+“充填+注浆”的二次接顶技术方案。一是将单点放料优化为多点放料;二是将矿房顶部空区 分成两段进行充填,减少因料浆流动不匀造成充填体与顶板之间的空区;最后采用“充填+注浆”方 式,对未实现接顶的空区进行加压注浆补缺。经工程实践验证,优化后的充填接顶方案效果较好, 接顶率 >92%,可进一步推广应用。

关键词: 大直径深孔, 一步采矿房, 分段充填, 注浆补缺, 接顶优化

Abstract: Improving the filling and roof contact effect of mining chamber first-step is of great signifi⁃ cance for ensuring the safe mining of the second-step mining chamber. In response to the problems such as large size of the void area in the high-stage large-diameter deep-hole mining area of Zhongguan Iron Mine and poor filling and roof contact effect,a filling slurry flow model of the mining area was constructed. Com⁃ bined with production practice,the settlement mechanism of the filling slurry in the void area was ana⁃ lyzed. It was found that when a single point was discharged and the filling slurry flowed over a long dis⁃ tance,in the void area,it often accumulated into a filling slope centered on the discharge port,with a higher middle part and lower periphery. Based on this,a secondary roof contacted technology scheme of segmented filling+"filling+grouting" was proposed. One is to optimize the single-point discharge to multi⁃ ple-point discharge; the other is to divide the top void area of the mining chamber into two sections for fill⁃ ing,reducing the void area between the filling body and the roof caused by uneven slurry flow. Finally,the "filling + grouting" method was adopted to conduct pressure grouting to fill the un-contacted void area. Through engineering practice,the optimized filling and roof contacted scheme has shown good results, with a roof contacted rate of over 92%,and can be further promoted and applied.

Key words: large diameter deep-hole, first-step mining chamber, stage filling, grouting to fill the gap, roof contact optimization