某煤矿突出煤层综掘面快速注水降尘技术的应用

杨俊磊   

  1. 中煤科工集团重庆研究院有限公司
  • 出版日期:2026-03-25 发布日期:2026-04-07

Application of Rapid Water Injection and Dust Reduction Technology in Fully Mechanized Excavation Face of Outburst Coal Seam in a Coal Mine

  1. CCTEG Chongqing Research Institute
  • Online:2026-03-25 Published:2026-04-07

摘要: 为解决某煤矿突出煤层综掘工作面粉尘浓度超标问题,并保障正常生产,基于突出 煤层综掘面快速注水机理,采用现场试验方法,开展了快速注水降尘技术的应用研究。结果表明: 利用分段膨胀式封孔器实施的突出煤层快速注水,可通过分段注水实现钻孔全深度煤体的均匀湿 润,即前段注水后应力集中带向深部转移,为后段注水提供渗流通道,有效增强煤体塑性;该技术 可充分利用既有探放水钻孔,将注水作业安排在皮带延伸期完成,不干扰正常生产,且分段式封孔 器操作简便、封孔高效。现场试验验证,在注水压力 12~14 MPa、注水时间 2.5 h 的参数下,单孔注 水量可达 1.6 m3 ,煤层湿润半径达 1.5 m 以上;注水后,综掘机司机位置粉尘浓度由 2 396.7 mg/m3 降 至 907.7 mg/m3 ,降尘效率达 62.1%,显著改善了工作面作业环境。研究证实,该快速注水降尘技术 适配突出煤层综掘面生产需求,具有良好的工程推广价值。

关键词: 突出煤层, 综掘工作面, 分段膨胀式封孔器, 注水降尘

Abstract: In order to solve the problem of dust concentration exceeding the standard in fully mecha‐ nized excavation face of outburst coal seam in a coal mine and ensure normal production,based on the mechanism of rapid water injection in fully mechanized excavation face of outburst coal seam,the applica‐ tion of rapid water injection and dust reduction technology is carried out by field test method. The results show that the rapid water injection of the outburst coal seam implemented by the segmented expansion hole sealing device can realize the uniform wetting of the coal body at the full depth of the borehole through the segmented water injection,that is,the stress concentration zone is transferred to the deep part after the wa‐ ter injection in the front section,which provides a seepage channel for the water injection in the back sec‐ tion and effectively enhances the plasticity of the coal body. The technology can make full use of the exist‐ ing water exploration and drainage boreholes,arrange the water injection operation to be completed during the extension period of the belt,do not interfere with the normal production,and the segmented hole pack‐ er is easy to operate and the hole sealing is efficient. The field test verifies that under the parameters of wa‐ ter injection pressure of 12~14 MPa and water injection time of 2.5 h,the water injection volume of a sin‐ gle hole can reach 1.6 m3 ,and the wetting radius of coal seam can reach more than 1.5 m. After water in‐ jection,the dust concentration at the driver's position of the roadheader decreased from 2 396.7 mg/m3 to 907.7 mg/m3 ,and the dust reduction efficiency reached 62.1%,which significantly improved the working environment of the working face. The research proves that the rapid water injection and dust reduction tech‐ nology is suitable for the production demand of fully mechanized excavation face of outburst coal seam, and has good engineering promotion value.

Key words: outburst coal seam, fully mechanized excavation face, segmented expansion hole sealing device, water injection and dust reduction