Modern Mining ›› 2020, Vol. 36 ›› Issue (09): 91-.
Previous Articles Next Articles
WU Chungang
Online:
Published:
Abstract: Based on the detailed introduction of the firstphase system engineering,it is proposed to carry out deep exploitation project construction to achieve the purpose of increasing productivity.For this purpose,several schemes are compared.After technical and economic demonstrations,the seamless docking scheme between beltinclined mine transportation and the firstphase crushed lower ore bin is finally determined,which solves the problem of secondary transportation of deep mine,saves costs and achieves ideal results.The construction of deep exploitation project provides a good example for other similar projects.
Key words: deep exploitation,beltinclined mine,seamless docking scheme,scheme optimization
WU Chungang. Optimum Practice of Exploitation Project Scheme for Deep Ore Body in Liguanji Iron Mine[J]. Modern Mining, 2020, 36(09): 91-.
/ Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: https://www.xdky.net/EN/
https://www.xdky.net/EN/Y2020/V36/I09/91