现代矿业 ›› 2013, Vol. 29 ›› Issue (11): 1-4.

• 采选工程 •    下一篇

李楼铁矿厚大矿体安全回采研究

朱国涛,郝红星,王晓飞   

  1. 五矿邯邢矿业安徽开发矿业有限公司
  • 出版日期:2013-11-15 发布日期:2014-04-08

Research on the Safety Stoping Method of the Large and Thick Orebody of Lilou Iron Ore

Zhu Guotao,Hao Hongxing,Wang Xiaofei   

  1. Anhui Mining Development Co.,Ltd.,Minmetals Hanxing Mining Co.,Ltd.
  • Online:2013-11-15 Published:2014-04-08

摘要: 介绍了高阶段深孔空场嗣后充填采矿方法在李楼铁矿的应用,同时开展井下大型采场开采过程中稳定性研究,确定采场结构尺寸宽、高不变,将矿房或矿柱分2~3部分进行回采,达到预期效果,取得良好的经济效益。

关键词: 厚大矿体, 暴露面积, 高阶段深孔空场嗣后充填法, 分部回采

Abstract: The application of the long hole open stope filling later method of high phase in the Lilou iron ore is introducted.At the same time ,the stability of mining process of the large underground stope is researched at length.Accroding to the research findings,the width and height of the stope structure are unchanged.The ore room or pillar is divided into 2~3 sections,and they are recoveried respectively so as to achieve the desired effect and obtain good economic benefits.

Key words: Large and thick orebody, Exposed area, Long hole open stope filling later method of high phase, Stoping sections