阿希金矿采矿过渡期隔离层厚度的确定

李振振   

  1. 新疆有色金属研究所
  • 出版日期:2012-10-15 发布日期:2012-11-09

Isolation Layer Thickness Confirmation of Mining Transition Period of Axi Gold Mine

Li Zhenzhen   

  1. Xinjiang Research Institute of Non Ferrous Metals
  • Online:2012-10-15 Published:2012-11-09

摘要: 针对新疆阿希金矿采矿过渡期要求,采用5种不同的过渡层厚度计算方法对过渡期的隔离层进行了计算,确定了符合阿希金矿生产要求的隔离层厚度。

关键词: 隔离层厚度, 深部充填法采矿, 过渡期采矿

Abstract: Aiming at the requirement of transition period of Axi Gold Mine of Xinjiang, isolation layer thickness of transition period was calculated by adopted five different kinds of transition layer thickness calculation method, isolation layer thickness which met the production requirement of Axi gold mine was confirmed after each calculation result consideration.

Key words: Isolation layer, Deep filling mining method, Transition period mining